Determination by the Federal Network Agency - AZ 622-22-008
On 23.11.2022, the list of measures submitted by the TSOs to the Federal Network Agency for the grid restoration plan was approved with regard to the regulations for SNN (significant grid users). A large amount of feedback from SNNs and DSOs (distribution system operators) was taken into account in the process. The task now is to implement the measures contained in the plan and to meet the deadlines set for the SNN in relation to the date of approval.
However, the measures for DSOs and TSOs are not subject to approval by the Federal Network Agency. The TSOs are responsible for defining all necessary measures and consulting with the stakeholders concerned when updating and adapting their grid restoration plans.
This has been done via the process of creating the catalog of measures for the grid restoration plan. The TSOs will therefore request the DSOs directly downstream of them to implement the measures in accordance with the defined implementation deadlines (start date 01.01.2023). The catalog of measures will therefore also become an annex to the respective grid restoration concepts of the TSOs. The DSOs are also requested to ask their downstream DSOs that are affected by the provisions of the catalog of measures to implement the measures that affect them.
The approval of the catalog of measures and the associated decision of the Federal Network Agency with the file number AZ 622-22-008 can be viewed under EU approval procedures (as of 12.12.2022) under "Completed procedures". You can also download the catalog of measures here:
12.12.2022 Anlage 1 – Maßnahmenkatalog (in German)
Finally, the TSOs would like to point out that a list of the Network Statement was submitted with this submission, which refers to the threshold definitions of resolution BK6-16-166. Due to the immense scope and the short-lived nature of the continuous changes, it is not feasible to compile an exhaustive list of all the SNNs.